Back to projects

Water Systems Upgrade

Saint-Siméon, Quebec

completeWastewaterGIS
Federal contribution
$213,140
Federal share40%

of $532.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Siméon
Construction start
Aug 9, 2021(actual)
Construction end
Oct 29, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast May 10, 2021
  • Construction end4 months lateforecast Jul 9, 2021