Modification of the guard post according to the division of the two care units and perform various interventions aimed at bringing universal accessibility up to standard

Saint-Siméon, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$228,000
Federal share80%

of $285.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2022(actual)
Construction end
Jul 31, 2023(actual)

Against the original forecast

  • Construction start13 months lateforecast Oct 1, 2021

Also in Saint-Siméon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59043 in the federal list. How to read these figures.