Water Systems Upgrades
Federal contribution
$379,090
Federal share40%
of $947.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2020
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Clermont
- Construction start
- May 25, 2020(actual)
- Construction end
- Nov 20, 2020(actual)
Against the original forecast
- Construction end4 months lateforecast Jul 10, 2020
Also in Clermont
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56309 in the federal list. How to read these figures.