Back to projects

Renewal of water pipes

Clermont, Quebec

completeDrinking WaterCWWF
Federal contribution
$588,247
Federal share50%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Clermont
Construction start
Aug 1, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast May 29, 2017
  • Construction end3 months earlyforecast Mar 31, 2018

Also in Clermont

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48817 in the federal list. How to read these figures.