Sechelt - Accessible Performance Space for Hackett Park
Federal contribution
$101,200
Federal share40%
of $253.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022
Built
Approved 8 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- District of Sechelt
- Construction start
- Feb 14, 2022(actual)
- Construction end
- Jun 29, 2022(actual)
Against the original forecast
- Construction start7 weeks lateforecast Dec 27, 2021
- Construction end2 weeks lateforecast Jun 15, 2022
Also in Sechelt
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56317 in the federal list. How to read these figures.