Back to projects

Sechelt - Accessible Performance Space for Hackett Park

Sechelt, British Columbia

completeCultureCCRIS
Federal contribution
$101,200
Federal share40%

of $253.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
20212022
Built

Approved 8 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
District of Sechelt
Construction start
Feb 14, 2022(actual)
Construction end
Jun 29, 2022(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Dec 27, 2021
  • Construction end2 weeks lateforecast Jun 15, 2022

Also in Sechelt

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56317 in the federal list. How to read these figures.