Water Systems Upgrade
Sainte-Catherine-de-la-Jacques-Cartier, Quebec
Federal contribution
$647,570
Federal share40%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2020
20212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Sainte-Catherine-de-la-Jacques-Cartier
- Construction start
- Jun 22, 2020(actual)
- Construction end
- Sep 18, 2025(actual)
Against the original forecast
- Construction start14 months earlyforecast Aug 9, 2021
- Construction end7 weeks lateforecast Jul 31, 2025
Also in Sainte-Catherine-de-la-Jacques-Cartier
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56326 in the federal list. How to read these figures.