Renewal of water pipes
Sainte-Catherine-de-la-Jacques-Cartier, Quebec
Federal contribution
$1.4M
$1,414,886
Federal share24%
of $5.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2017
201720182019
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Sainte-Catherine-de-la-Jacques-Cartier
- Construction start
- May 6, 2019(actual)
- Construction end
- Oct 31, 2019(actual)
Also in Sainte-Catherine-de-la-Jacques-Cartier