Water Systems Upgrades
Federal contribution
$383,725
Federal share40%
of $959.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
2021202220232024
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Lévis
- Construction start
- Aug 14, 2023(actual)
- Construction end
- Jun 13, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2023
- Construction end6 months lateforecast Nov 30, 2023
Also in Lévis
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56440 in the federal list. How to read these figures.