Back to projects

Water Systems Upgrades

Lévis, Quebec

completeWastewaterGIS
Federal contribution
$383,725
Federal share40%

of $959.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
2021202220232024
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Lévis
Construction start
Aug 14, 2023(actual)
Construction end
Jun 13, 2024(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2023
  • Construction end6 months lateforecast Nov 30, 2023