Water Systems Upgrades
Federal contribution
$991,572
Federal share40%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Lévis
- Construction start
- Aug 29, 2022(actual)
- Construction end
- Jul 13, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast May 2, 2022
- Construction end2 weeks lateforecast Jun 26, 2023
Also in Lévis
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56442 in the federal list. How to read these figures.