Water Systems Upgrades

Saint-Lambert, Quebec

completeWastewaterGIS
Federal contribution
$785,398
Federal share40%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
202120222023
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Construction start
May 10, 2021(actual)
Construction end
Sep 8, 2023(actual)

Against the original forecast

  • Construction end11 months lateforecast Oct 14, 2022