Repair of the corridors of Block F at the Campus Saint-Lambert

Saint-Lambert, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$410,000
Federal share68%

of $606.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 10, 2021(actual)
Construction end
Aug 9, 2021(actual)

Against the original forecast

  • Construction end5 weeks earlyforecast Sep 15, 2021

Also in Saint-Lambert

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59179 in the federal list. How to read these figures.