Water System Upgrades

Montréal, Quebec

completeWastewaterGIS
Federal contribution
$4.0M
$3,953,025
Federal share40%

of $9.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 20, 2020
202120222023
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Montréal
Construction start
Jun 30, 2020(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction end3 months lateforecast Dec 31, 2022