Water System Upgrades

Montréal, Quebec

completeWastewaterGIS
Federal contribution
$4.0M
$3,986,887
Federal share40%

of $10.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 20, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Montréal
Construction start
Jun 30, 2020(actual)
Construction end
Jun 30, 2021(actual)

Against the original forecast

  • Construction end3 months earlyforecast Sep 30, 2021