Water System Upgrades
Federal contribution
$2.3M
$2,343,549
Federal share40%
of $5.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 20, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Montréal
- Construction start
- Jun 30, 2020(actual)
- Construction end
- Mar 31, 2023(actual)
Against the original forecast
- Construction start14 months earlyforecast Aug 16, 2021
- Construction end5 months lateforecast Oct 31, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56570 in the federal list. How to read these figures.