French Community of Calgary Roof and Common Areas Renovation

Calgary, Alberta

completeRecreationCCRIS
Federal contribution
$164,525
Federal share38%

of $427.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 1, 2020
2021
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Aug 1, 2020(actual)
Construction end
Jun 15, 2021(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 5, 2020
  • Construction end2 weeks earlyforecast Jun 30, 2021