Schedule

Announced and approvedAug 25, 2020
2021
Built

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Aug 13, 2020(actual)
Construction end
Aug 30, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 26, 2020
  • Construction end2 months lateforecast Jun 30, 2021