Calgary - Downtown Flood Barrier
Federal contribution
$6.1M
$6,138,754
Federal share33%
of $18.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 26, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Calgary
- Construction start
- Jul 26, 2021(actual)
- Construction end
- Oct 13, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 15, 2021
- Construction end6 weeks lateforecast Sep 4, 2023
Also in Calgary
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56623 in the federal list. How to read these figures.