Calgary - Upper Plateau Separation
Federal contribution
$14.7M
$14,740,000
Federal share40%
of $36.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 26, 2020
20212022202320242025
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Calgary
- Construction start
- Nov 19, 2021(actual)
- Construction end
- Nov 29, 2024(actual)
Against the original forecast
- Construction start3 weeks lateforecast Nov 1, 2021
- Construction end5 months lateforecast Jul 15, 2024