Coaldale Malloy Drain Phase 2B Implementation Plan
Federal contribution
$1.3M
$1,260,797
Federal share40%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 26, 2020
20212022202320242025
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Coaldale
- Construction start
- Jan 13, 2025(actual)
- Construction end
- Apr 9, 2025(actual)
Against the original forecast
- Construction start8 weeks lateforecast Nov 18, 2024
- Construction end6 months earlyforecast Sep 30, 2025