2022 Walking & Biking Pathway Project - Town of Coaldale, Province of Alberta
Federal contribution
$100,774
Federal share60%
of $168.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 26, 2024
20232024
Built
Approved 23 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Coaldale
- Construction start
- Aug 30, 2022(actual)
- Construction end
- Oct 20, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2022
- Construction end3 months lateforecast Jul 27, 2022
Also in Coaldale
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63615 in the federal list. How to read these figures.