Back to projects

Town of Taber - Water Treatment Plant pH Adjustment Carbon Dioxide Injection

Taber, Alberta

completeDrinking WaterGIS
Federal contribution
$166,008
Federal share40%

of $415.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 4, 2020
2021
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Taber
Construction start
Jul 12, 2021(actual)
Construction end
Nov 8, 2021(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 15, 2021
  • Construction end5 months earlyforecast Mar 31, 2022

Also in Taber

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56671 in the federal list. How to read these figures.