Town of Taber - Water Treatment Plant pH Adjustment Carbon Dioxide Injection
Federal contribution
$166,008
Federal share40%
of $415.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 4, 2020
2021
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Taber
- Construction start
- Jul 12, 2021(actual)
- Construction end
- Nov 8, 2021(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 15, 2021
- Construction end5 months earlyforecast Mar 31, 2022
Also in Taber
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56671 in the federal list. How to read these figures.