Saddle Hills County - Central Peace Regional Water (Phase 1 and 2)
Federal contribution
$16.0M
$16,000,000
Federal share40%
of $40.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 2, 2020
today
2021202320252027
BuiltForecast
Approved 7 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- County of Saddle Hills
- Construction start
- Nov 21, 2024(actual)
- Construction end
- Sep 30, 2027(forecast)