Woking Lift Station upgrade

Saddle Hills County, Alberta

completeWastewaterCWWF
Federal contribution
$224,822
Federal share44%

of $510.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
County of Saddle Hills
Construction start
May 18, 2018(actual)
Construction end
Jul 11, 2019(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2018
  • Construction end3 weeks earlyforecast Jul 31, 2019

Also in Saddle Hills County