Back to projects

Town of Rocky Mountain House - Regional Wastewater Treatment Facility

Rocky Mountain House, Alberta

underwayWastewaterRNIS
Federal contribution
$10.9M
$10,889,200
Federal share40%

of $27.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 25, 2020
202120222023202420252026
BuiltForecast

Approved 5 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jun 22, 2023(actual)
Construction end
Jul 15, 2026(forecast)

Against the original forecast

  • Construction start3 months lateforecast Mar 30, 2023