OChiese First Nation (OCFN) Baptiste River Bridge Replacement
Federal contribution
$12.7M
$12,650,000
Federal share89%
of $14.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 29, 2024
today
202520262027
BuiltForecast
Approved 4 months before the announcement.
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- O'Chiese First Nation
- Construction start
- Jun 8, 2026(actual)
- Construction end
- Oct 6, 2027(forecast)