Potable Water Dispensing Unit
St. Lunaire-Griquet, Newfoundland and Labrador
Federal contribution
$145,093
Federal share40%
of $362.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2020
202120222023
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. Lunaire-Griquet
- Construction start
- Jul 18, 2022(actual)
- Construction end
- Jul 21, 2023(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2022
- Construction end7 months lateforecast Dec 31, 2022