Dark Tickle Sewer System
St. Lunaire-Griquet, Newfoundland and Labrador
Federal contribution
$131,299
Federal share50%
of $262.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of St. Lunaire-Griquet
- Construction start
- Sep 13, 2017(actual)
- Construction end
- Oct 4, 2017(actual)
Against the original forecast
- Construction start10 months lateforecast Nov 1, 2016
- Construction end10 months earlyforecast Jul 31, 2018
Also in St. Lunaire-Griquet
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47064 in the federal list. How to read these figures.