Water Systems Upgrades

Candiac, Quebec

completeWastewaterGIS
Federal contribution
$1.3M
$1,317,194
Federal share40%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Candiac
Construction start
May 17, 2021(actual)
Construction end
Sep 30, 2022(actual)

Against the original forecast

  • Construction end3 months lateforecast Jul 15, 2022