A redesigned school zone to encourage active mobility for Candiac schoolchildren

Candiac, Quebec

completeCapacity BuildingATF
Federal contribution
$48,295
Federal share69%

of $70.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 5, 2025
202320242025
Built

Approved 2.5 years before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Candiac
Construction start
Aug 25, 2022(actual)
Construction end
Sep 1, 2025(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jul 1, 2022
  • Construction end22 months lateforecast Oct 31, 2023