Manganese and Iron Treatment System
Federal contribution
$901,589
Federal share40%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
20212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Scott
- Construction start
- Apr 25, 2022(actual)
- Construction end
- Feb 7, 2025(actual)
Against the original forecast
- Construction end6 months lateforecast Aug 9, 2024
Also in Scott
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56814 in the federal list. How to read these figures.