All-season multipurpose trail in Scott

Scott, Quebec

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 5, 2025
202320242025
Built

Approved 2.5 years before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Municipality of Scott
Construction start
Mar 22, 2023(actual)
Construction end
Jul 1, 2025(actual)

Against the original forecast

  • Construction start11 months lateforecast May 3, 2022
  • Construction end2.3 years lateforecast Feb 28, 2023