All-season multipurpose trail in Scott
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 5, 2025
202320242025
Built
Approved 2.5 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Municipality of Scott
- Construction start
- Mar 22, 2023(actual)
- Construction end
- Jul 1, 2025(actual)
Against the original forecast
- Construction start11 months lateforecast May 3, 2022
- Construction end2.3 years lateforecast Feb 28, 2023