Valley Road Sewer Upgrade
Carbonear, Newfoundland and Labrador
Federal contribution
$411,187
Federal share40%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 23, 2020
2021
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Carbonear
- Construction start
- Jul 19, 2021(actual)
- Construction end
- Nov 3, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 10, 2021
- Construction end19 months earlyforecast May 30, 2023
Also in Carbonear
- Upgrades to Route 70- Interchange at Valley Road and Route 75 - Veterans Memorial Highway$2.2M
- Water System Upgrading$807.0K
- Adelaide Street Water Sewer Storm Street Upgrades Ph2$587.6K
- Water Street Water, Sewer and Street Upgrading$517.8K
- Water Street - Water, Sewer and Street Upgrading Phase 3$473.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56820 in the federal list. How to read these figures.