Back to projects

Valley Road Sewer Upgrade

Carbonear, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$411,187
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 23, 2020
2021
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Carbonear
Construction start
Jul 19, 2021(actual)
Construction end
Nov 3, 2021(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 10, 2021
  • Construction end19 months earlyforecast May 30, 2023

Also in Carbonear

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56820 in the federal list. How to read these figures.