Back to projects

Goulds Servicing - Phase 2

St. John's, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$4.1M
$4,114,613
Federal share40%

of $10.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2022
2021202220232024
Built

Approved 2 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of St. John's
Construction start
Oct 11, 2021(actual)
Construction end
Apr 16, 2024(actual)

Against the original forecast

  • Construction start6 months lateforecast Mar 30, 2021
  • Construction end4 months lateforecast Dec 15, 2023

Also in St. John's