Marshall Drive Water, Sewer and Street Upgrading

Carbonear, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$83,578
Federal share40%

of $208.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 23, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Carbonear
Construction start
Jul 29, 2021(actual)
Construction end
Oct 15, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 10, 2021
  • Construction end12 months earlyforecast Oct 30, 2022

Also in Carbonear

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56848 in the federal list. How to read these figures.