Water Street Infrastructure Rehabilitation - Phase 4

St. John's, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$2.9M
$2,894,226
Federal share40%

of $7.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
20212022202320242025
Built

Approved 4.7 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of St. John's
Construction start
Mar 29, 2021(actual)
Construction end
Jun 21, 2021(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 1, 2021
  • Construction end3 years earlyforecast Jun 30, 2024