Carson Crescent Storm Sewer Installation
Channel-Port aux Basques, Newfoundland and Labrador
Federal contribution
$120,456
Federal share18%
of $682.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2021
2021
Built
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Channel-Port aux Basques
- Construction start
- May 21, 2021(actual)
- Construction end
- Aug 13, 2021(actual)
Against the original forecast
- Construction end6 weeks lateforecast Jul 1, 2021