Blivet Treatment Plant

Placentia, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$265,234
Federal share40%

of $663.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 14, 2021
20212022
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Placentia
Construction start
Jun 13, 2022(actual)
Construction end
Aug 1, 2022(actual)

Against the original forecast

  • Construction start3 months earlyforecast Sep 1, 2022
  • Construction end2 months earlyforecast Oct 15, 2022