Cox Avenue Road Construction

Channel-Port aux Basques, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$184,687
Federal share30%

of $616.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
2021
Built

Approved 11 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
May 25, 2021(actual)
Construction end
Aug 31, 2021(actual)

Against the original forecast

  • Construction end2 months lateforecast Jul 1, 2021

Also in Channel-Port aux Basques

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56881 in the federal list. How to read these figures.