Queen Street Extension
Stephenville, Newfoundland and Labrador
Federal contribution
$267,006
Federal share40%
of $667.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2021
2021
Built
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Stephenville
- Construction start
- May 17, 2021(actual)
- Construction end
- Aug 12, 2021(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jun 30, 2021
- Construction end3 weeks earlyforecast Aug 31, 2021