Intake Screen Cleaning System
Forresters Point, Newfoundland and Labrador
Federal contribution
$21,351
Federal share40%
of $53.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2020
20212022
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Local Service District of Forrester's Point
- Construction start
- Jul 29, 2022(actual)
- Construction end
- Sep 19, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast May 2, 2022
- Construction end4 months lateforecast Jun 1, 2022