Community Water System Improvement

Forresters Point, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$150,569
Federal share50%

of $301.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Jul 16, 2018(actual)
Construction end
Aug 21, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2018
  • Construction end9 months lateforecast Nov 30, 2018