Conventional Transit Vehicle Expansion
Federal contribution
$3.1M
$3,123,606
Federal share40%
of $7.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 8, 2020
2021202220232024
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Corporation of the City of Burlington
- Construction start
- Jul 14, 2020(actual)
- Construction end
- Sep 13, 2024(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Sep 30, 2024
Also in Burlington
- Halton Region Wastewater Treatment (Skyway Facility)$51.4M
- Replacement of Access Points; Open Concept Schools; Building Automation Systems & Controls Upgrade; Child Care Retrofits & Outdoor Spaces$6.9M
- Portable Classroom Ventilation Improvements; HVAC Improvements; Window Replacement$5.6M
- Improvements to HVAC, Windows, Bottle Filling Stations, Washrooms, Doors, Child Care Centre, WiFi and Network Infrastructure$5.4M
- Highway 403 - Rehabilitation and Resurfacing$4.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56931 in the federal list. How to read these figures.