Leary's Brook Berm
St. John's, Newfoundland and Labrador
Federal contribution
$780,610
Federal share50%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20212022
Built
Approved 12 months before the announcement.
- Program
- Green Infrastructure Stream
- Construction start
- Aug 26, 2020(actual)
- Construction end
- Mar 21, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2020
- Construction end4 months lateforecast Nov 30, 2021
Also in St. John's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56953 in the federal list. How to read these figures.