Annex Stadium
Deer Lake, Newfoundland and Labrador
Federal contribution
$1.5M
$1,541,257
Federal share33%
of $4.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2020
20212022202320242025
Built
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Deer Lake
- Construction start
- May 1, 2022(actual)
- Construction end
- May 13, 2025(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 1, 2022
- Construction end4 months lateforecast Jan 21, 2025
Also in Deer Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57029 in the federal list. How to read these figures.