Back to projects

Water Filter Replacement

Deer Lake, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$966,213
Federal share40%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2022202320242025
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Deer Lake
Construction start
Sep 7, 2023(actual)
Construction end
Nov 13, 2024(actual)

Against the original forecast

  • Construction start4 months lateforecast May 3, 2023
  • Construction end4 months lateforecast Jul 18, 2024

Also in Deer Lake