Selkirk Street Stormwater
Federal contribution
$2.6M
$2,561,883
Federal share75%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2021
202120222023
Built
Approved 13 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Whitehorse
- Construction start
- Sep 4, 2021(actual)
- Construction end
- Nov 2, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast May 3, 2021
- Construction end3 months lateforecast Jul 31, 2023
Also in Whitehorse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57052 in the federal list. How to read these figures.