Selkirk Street Stormwater

Whitehorse, Yukon

completeDrinking WaterGIS
Federal contribution
$2.6M
$2,561,883
Federal share75%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2021
202120222023
Built

Approved 13 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Whitehorse
Construction start
Sep 4, 2021(actual)
Construction end
Nov 2, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast May 3, 2021
  • Construction end3 months lateforecast Jul 31, 2023