Back to projects

Water System Expansion - Phase 3

Memramcook, New Brunswick

underwayDrinking WaterRNIS
Federal contribution
$5.0M
$5,020,408
Federal share60%

of $8.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2021
today
2021202320252027
BuiltForecast

Approved 5 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Village of Memramcook
Construction start
May 25, 2021(actual)
Construction end
Dec 31, 2026(forecast)

Against the original forecast

  • Construction start5 months lateforecast Dec 15, 2020

Also in Memramcook

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57071 in the federal list. How to read these figures.