Water Supply Extension - Phase 2
Federal contribution
$743,281
Federal share50%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
20172018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Memramcook
- Construction start
- Jul 4, 2017(actual)
- Construction end
- Nov 4, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2017
- Construction end5 months earlyforecast Mar 31, 2019
Also in Memramcook
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48187 in the federal list. How to read these figures.