Village of Torquay Water Treatment Plant Upgrades

Torquay, Saskatchewan

completeDrinking WaterGIS
Federal contribution
$744,408
Federal share40%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2021
202120222023
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Torquay
Construction start
Jun 1, 2022(actual)
Construction end
Aug 30, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2022