Village of Torquay - Community Center Upgrades
Federal contribution
$79,916
Federal share40%
of $199.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
20222023
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Village of Torquay
- Construction start
- Apr 1, 2022(actual)
- Construction end
- May 26, 2023(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2021
- Construction end5 months lateforecast Dec 31, 2022
Also in Torquay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59316 in the federal list. How to read these figures.