Back to projects

Village of Torquay - Community Center Upgrades

Torquay, Saskatchewan

completeRecreationCVRIS
Federal contribution
$79,916
Federal share40%

of $199.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 6, 2021
20222023
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Village of Torquay
Construction start
Apr 1, 2022(actual)
Construction end
May 26, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 15, 2021
  • Construction end5 months lateforecast Dec 31, 2022